Question No.211

You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

  1. Report Program Performance

  2. Monitor and Control Program Scope

  3. Monitor and Control Program Schedule

  4. Monitor and Control Program Performance

Correct Answer: C

Question No.212

You are working with Sam, a project manager on one of the projects within your program. Sam doesn#39;t understand all of the rules and procedures that he#39;s required to do as a project manager in your program. What are the rules and procedures called in project that Sam must abide by?

  1. Project governance

  2. Process procedures

  3. Enterprise environmental factors

  4. Program governance

Correct Answer: C

Question No.213

Which of the following is described in the statement given below?

quot;It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication.quot;

  1. Stakeholder register

  2. Program scope statement

  3. Governance plan

  4. Organizational chart

Correct Answer: A

Question No.214

Which of the following statements are true regarding program scope statement?

  1. It defines all the work and only the required work for the program.

  2. It formally authorizes the program.

  3. It sets authorities and limits for the program manager and team.

  4. It represents a common understanding of the program for the purpose of facilitating communication among the stakeholders.

Correct Answer: ACD

Question No.215

You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you#39;ve assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are telling Beth about the five process groups of project management and how they map to the progression of the project. Which process group would you tell Beth is where she#39;ll likely spend the bulk of the project time and the project budget?

  1. Monitoring and Controlling

  2. Planning

  3. Executing

  4. Procurement

Correct Answer: C

Question No.216

A project manager in your program is using progress elaboration as part of their planning approach. This approach is also known as what planning methodology?

  1. Waterfall management

  2. Rolling wave planning

  3. Scope refinements

  4. Incremental planning

Correct Answer: B

Question No.217

Who makes Go/No-Go decisions during phase gate reviews?

  1. Program Governance board

  2. Program Manager

  3. Board of Project Managers

  4. Stakeholders

Correct Answer: A

Question No.218

Which of the following tools/techniques keep program managers and executives informed of the program#39;s progress?

  1. Component analysis

  2. Expert judgment

  3. Review meetings

  4. Capacity planning

Correct Answer: C

Question No.219

You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?

  1. Audit reports

  2. Program management plan

  3. Program performance reports

  4. Program issues register updates

Correct Answer: D

Question No.220

You are a program manager for an environmental program. The program involves installation of windmill across the country. During execution of the project, a stakeholder raises a change request to add an additional module with the existing installation. The program governance board has approved the change request. Which of the following is true regarding this scenario?

  1. The new Program Master Schedule is created containing the approved changes.

  2. Separate project is made to ensure that the approved changes are included in the program.

  3. Project charter is upgraded to include the approved changes in the program.

  4. The Program Master Schedule is updated to reflect the changes.

Correct Answer: D